I-35W Bridge Construction On Schedule
MnDot Project Manager John Chiglo said workers made good progress on rebuilding the I-35W bridge in Minneapolis over the winter. Chiglo said workers continue to maintain a good safety record and a barge from Lousiana has arrived and is in place to construct a crane to put bridge segments into position. Chiglo said bridge workers have poured more than half of the bridge platforms and will continue to pour segments through the month of May. Chiglo said interested citizens could get weekly updates on the bridge progress by going to the MnDot web site www.mndot.gov and sign up for the service.